Need Integrated system solutions diagram to portray/illustrate our projct: http://nasascience.nasa.gov/earth*science/applied*sciences/solicitations/information*to*support*proposals
+
Need Integrated system solutions diagram to portray/illustrate our project: http://nasascience.nasa.gov/earth*science/applied*sciences/solicitations/information*to*support*proposals
 
+
* [http://nasascience.nasa.gov/earth-science/applied-sciences/solicitations/ISS_chart_download.ppt blank diagram]
  
 
===Proposal summary:===
 
===Proposal summary:===
Line 23: Line 23:
 
* Approach to quantify improvements in the system performance (risk/uncertainty)
 
* Approach to quantify improvements in the system performance (risk/uncertainty)
 
* approach to quantify socioeconomic value and benefits for resulting improvements
 
* approach to quantify socioeconomic value and benefits for resulting improvements
* key technical, policy, operation and magement challenges and the approach to address challenges
+
* key technical, policy, operation and engagement challenges and the approach to address challenges
* describe tools, system, assessment in detail including decisiion analysis factors, unique roles for E.S. data and other pertinent info.
+
* describe tools, system, assessment in detail including decision analysis factors, unique roles for E.S. data and other pertinent info.
  
  
Line 33: Line 33:
 
===Performance Measures: ===
 
===Performance Measures: ===
 
* Quantitative/Qualitative measures of outcome, results and value of project
 
* Quantitative/Qualitative measures of outcome, results and value of project
 +
 +
other performance measures:
 +
* forecast skill scores
 +
* change in planning time
 +
* change in response time (e.g. disaster response time)
 +
* percentage of population served
 +
* level or certainty/uncertainty in the decision support system
 +
* false negatives/false positives
 +
* exposure assessment time and accuracy
 +
* control measure effectiveness
  
 
===Anticipated results===
 
===Anticipated results===
Line 47: Line 57:
 
** Plans for delivery of project results  
 
** Plans for delivery of project results  
 
** Final report
 
** Final report
 +
 +
Project metrics
 +
* Percent of tasks starting/ending as planned
 +
* Number (or percent) of deliverables meeting quality standards
 +
* Integration time of observations/model products into the decision support system
 +
* Delivery time of Earth science products
 +
* Costs for production of value-added products
 +
* Number of iterations to verify data product integration
 +
* Time to correct a problem
 +
* Milestones met ahead of schedule
 +
* Run-time for a decision support system
  
  
 
* Project schedule (1pg)
 
* Project schedule (1pg)

Latest revision as of 07:48, August 12, 2008

Need Integrated system solutions diagram to portray/illustrate our project: http://nasascience.nasa.gov/earth*science/applied*sciences/solicitations/information*to*support*proposals

Proposal summary:

  • Explicitly state which of NASA 8 areas the proposal relates to (if more than 2 identify top 3)
  • how does project respond to priority topic (AQ)

Decision Support:

  • describe activity
  • magangemt, policy, business topic or issue
  • identify end users
  • quantify pre*project baseline

E.S. Research Results:

  • Identify all data products used.

In Tech approach:

  • perceived impact of work
  • objectives and relevance to NASA past/present/future
  • Methodology
  • Systematic approach to integrate E.S. data into DSS and to develop and test integrated system
  • data sharing plan/provide evidence of past data sharing.
  • Approach to quantify improvements in the system performance (risk/uncertainty)
  • approach to quantify socioeconomic value and benefits for resulting improvements
  • key technical, policy, operation and engagement challenges and the approach to address challenges
  • describe tools, system, assessment in detail including decision analysis factors, unique roles for E.S. data and other pertinent info.


Transition Approach:

  • Articulate transition plan

( GEOSS AIP, tutorials with EPA)

Performance Measures:

  • Quantitative/Qualitative measures of outcome, results and value of project

other performance measures:

  • forecast skill scores
  • change in planning time
  • change in response time (e.g. disaster response time)
  • percentage of population served
  • level or certainty/uncertainty in the decision support system
  • false negatives/false positives
  • exposure assessment time and accuracy
  • control measure effectiveness

Anticipated results

  • State quantitative hypothesis
  • estimate expected improvements

Project Management: (2pg)

  • plan of work
  • Partnership arrangements
  • expected contribution, roles,responsibilities of team members
  • Milestones
    • For Biannual reports
    • demo/prototype needed 2x (1 proof of concept, 1 use and performance enhanced of decision*making activity)
    • Plans for delivery of project results
    • Final report

Project metrics

  • Percent of tasks starting/ending as planned
  • Number (or percent) of deliverables meeting quality standards
  • Integration time of observations/model products into the decision support system
  • Delivery time of Earth science products
  • Costs for production of value-added products
  • Number of iterations to verify data product integration
  • Time to correct a problem
  • Milestones met ahead of schedule
  • Run-time for a decision support system


  • Project schedule (1pg)